COBie 2.4 scope guide

What belongs in COBie?

COBie is meant to carry the products and equipment a facility team will manage, not every object in the model. This guide explains what COBie 2.4, as published in NBIMS-US V3, says about which assets and attributes belong in the workbook, and where the owner's requirements take over.

The short answer

COBie 2.4 records the scheduled products and equipment that will be installed and managed: each product as a Type and each installed instance as a Component. The US exclusion lists leave out walls, slabs, roofs, and structural framing; stairs, ramps, and railings; duct, pipe, and cable runs with their fittings; fasteners and openings; and other objects that are not managed assets. Within those limits, the owner's requirements and the contract set the final scope.

Start with the scheduled assets

NBIMS-US V3 defines Types as the different products and equipment to be installed in the facility, and Components as the individual installed instances of those Types (§4.2.3.2.2.54 and §4.2.3.2.2.85). Type and Component names must match the design drawing schedules for the same project stage (§4.2.3.2.2.55 and §4.2.3.2.2.86).

The schedules are the anchor. The standard says drawing-schedule information should be included in COBie and that comparing the schedules with the COBie file is the basis for assessing its quality (§4.2.5.2.4.9). Its summary of the COBie Guide calls that match the only non-negotiable quality standard for design COBie. Construction COBie then updates the same assets with construction and commissioning information consistent with the contractor's submittals (§4.2.9.1.1).

Early architectural drawings already schedule spaces, doors, windows, plumbing fixtures, and lighting fixtures, and the standard expects that information in COBie (§4.2.5.2.4.8). Equipment and fixture schedules from the engineering disciplines follow as the design develops.

A useful first test

If a product appears on a design schedule, expect it in COBie as a Type, with its installed instances as Components, unless the owner's scope says otherwise. If an object appears on no schedule, ask whether anyone will operate, maintain, or replace it before adding it.

What the US exclusion lists leave out

Section 4.2.7.15 lists the IFC entities to filter out when producing the generic US COBie data set: Table 101 covers the Type and Component worksheets, and Table 102 covers every worksheet. Annex A §A.4 shows the same lists on the IFC4 inheritance tree in Table 58 for types and Table 59 for instances. The COBie Responsibility Matrix describes these entities as not considered managed assets (§4.2.9.1.2).

Examples from the US entity exclusion lists, grouped by area
AreaLeft out of COBieStays eligible
Building fabricLeft out of COBieWalls and curtain walls, slabs, roofs, beams, columns, members, plates, footings, and pilesStays eligibleDoors, windows, coverings, shading devices, and chimneys
CirculationLeft out of COBieStairs, stair flights, ramps, ramp flights, and railingsStays eligibleTransport elements such as elevators and escalators
HVAC and plumbingLeft out of COBieDuct and pipe segments and their fittingsStays eligibleBoilers, chillers, coils, fans, pumps, compressors, valves, dampers, air terminals and terminal boxes, filters, tanks, heat exchangers, humidifiers, sanitary terminals, and interceptors
Electrical and communicationsLeft out of COBieCable and cable-carrier segments and their fittings, including junction boxesStays eligibleDistribution boards, switching and protective devices, transformers, generators, motors, light fixtures, lamps, outlets, appliances, and solar devices
Controls and fire protectionLeft out of COBieNoneStays eligibleSensors, actuators, alarms, controllers, flow instruments, flow meters, and fire suppression terminals
Parts and fixingsLeft out of COBieFasteners, mechanical fasteners, building element parts, element assemblies, and reinforcing bars and meshStays eligibleDiscrete accessories and vibration isolators
FurnishingsLeft out of COBieNoneStays eligibleFurniture and system furniture
Non-physical objectsLeft out of COBieAnnotations, openings, voids, projections, surface features, virtual elements, distribution ports, and structural analysis itemsStays eligibleNone

Buildings, storeys, and spaces are not Types or Components either. COBie records them on the Facility, Floor, and Space worksheets.

Apply the instance list to Component rows

The two Annex A tables are not identical. Roof, footing, pile, element assembly, building element part, mechanical fastener, and reinforcing bar and mesh types are not struck from the type table, but their instances are excluded in Table 59 and Table 101, so they do not become Components.

What stays eligible

Everything not on the lists remains eligible, which covers much more than mechanical plant. The table above gives examples; Annex A Tables 58 and 59 list every entity. Building element proxies are not excluded either, so generic modeled objects need a decision based on what they actually are.

Eligible is not the same as required. The exclusion lists say what is not a managed asset in the generic US data set; the owner's requirements decide which eligible products a project must deliver. Revit categories do not map one-to-one to IFC entities, so judge each type by its function rather than its category name.

Types also record whether a product is fixed or movable through Type.AssetType (§4.2.3.2.2.58), and Annex A Table 44 maps furniture types to Moveable.

The owner sets the final scope

The US lists are a baseline. Section 4.2.7.15 notes that owners may extend COBie to non-managed facility assets and advises software vendors to support contract-specific exclusion lists. Annex A adds that regional or contract-based lists are at the discretion of those regions or owners.

Section 4.2.9.1.1 describes COBie as designed for customization through owner-specific classifications, commonly required property sets, and space and product requirements, which owners document in Appendix A of the COBie Guide. Table 4 of the standard says the generic COBie Guide should be updated for an owner's requirements before COBie is specified.

Before setting the scope, ask for the owner's COBie requirements, responsibility matrix, or asset list. Where the contract adds items the generic lists leave out, or omits eligible items, the contract governs that project.

Every Component needs a Type and a Space

COBie's business rules check that product assets have a valid Type and that every Component is assigned to a Space (§4.2.6.2.3). The quality-control rules require Component.TypeName and Component.Space to reference existing rows, and the Type rules include a check named AComponentForEachType, so a Type without installed Components is flagged (§4.2.8.1.3).

  • Equipment that is not contained in a single space uses the Space from which it is most likely to be maintained (§4.2.3.2.2.88).
  • Products scheduled only by type still need a unique name for every Component, using a naming rule the contract specifies (§4.2.3.2.2.86).
  • A Type with no Components, or a Component without a Space, usually points to a scope or modeling gap rather than a data-entry task.

Which attributes belong

COBie does not define a universal property set for each kind of equipment. Section 4.2.6.2.1.34 places the standardization of property sets outside the COBie effort, and §4.2.6.2.1.35 notes that attribute sets for standard equipment types were not submitted for consensus review. In their absence, the COBie Guide says Attributes should match the product data properties on the associated contract deliverables, such as design schedules and manufacturers' data sheets.

Annex A §A.5 then lists properties that should not become Attribute rows when COBie is produced from IFC:

  • Modeling and layout metadata: Host, Phase, Phase Created, Mark, Symbol, Line Pattern, levels, offsets, and zones (§A.5.1).
  • Classification bookkeeping: Assembly, Category, Classification, OmniClass, and Uniclass codes and descriptions (§A.5.1).
  • Raw dimensions: Property names containing Height, Length, Radius, or Size, or starting with Width (§A.5.1).
  • Values with their own COBie fields: Serial number, installation date, warranty start date, tag number, bar code, and asset identifier, plus circuit number and system name and type (§A.5.2).
  • Values with dedicated Type columns: Manufacturer, model number, warranty terms, expected life, replacement cost, nominal dimensions, color, finish, material, and similar product fields (§A.5.3).
  • Space, Floor, and Facility fields: Space area, number, and zone name; Floor elevation; and Facility phase (§A.5.3).
  • Placeholder values: Any property whose value is "default" or matches its own name (§A.5).

These rules were written for IFC exports. In a Revit workflow, treat them as guidance rather than a literal name filter: check whether the information already has a dedicated COBie field before dropping it, and keep operating characteristics such as rated capacity even when every instance of a type shares the same value.

A practical scope checklist

  • Get the owner's COBie requirements, responsibility matrix, and any required asset list before modeling decisions are locked.
  • Start from the design schedules: every scheduled product should appear as a Type, with names that match the schedule.
  • Leave out walls, slabs, roofs, and structural framing; stairs, ramps, and railings; duct, pipe, and cable runs with their fittings; fasteners; and openings, unless the contract adds them.
  • Decide eligible but optional categories, such as coverings and furniture, against the owner's list.
  • Check that every Component references an existing Type and Space, using the maintenance access space for equipment that serves several rooms.
  • Keep Attributes that match schedules and data sheets; remove modeling metadata and values that belong in dedicated fields.
  • Review the scope again after each model update, when new families and types appear.

How BIMRelay applies this

In BIMRelay, asset rules decide which Revit categories, families, and types become Type and Component rows, and attribute settings decide which Revit parameters become Attribute rows. After each model extraction, Asset review compares that selection with the guidance above and recommends what to include or exclude, with the evidence behind each suggestion. A project manager previews and confirms any change.

Asset review suggests excluding rainwater downspouts, which behave like pipe runs rather than managed equipment. The grid shows the eight Component rows the recommendation covers.
See how Asset review works

Frequently asked questions

Should pipes and ducts be in COBie?
Not in the generic US data set. Duct, pipe, cable, and cable-carrier segments and their fittings, including junction boxes, are on the NBIMS-US exclusion lists. The equipment those runs connect, such as pumps, valves, dampers, and air terminals, remains eligible, and the System worksheet groups Components that provide a common function.
Do doors and windows belong in COBie?
They can. Doors and windows are not on the US exclusion lists, and NBIMS-US V3 names door and window schedules among the scheduled asset information COBie represents. The owner's requirements decide whether a project delivers them.
Is furniture included in COBie?
Furniture and system furniture are not on the US exclusion lists, and Annex A maps furniture types to an AssetType of Moveable. The lists only say what may be included, so check the owner's requirements before adding loose furniture.
Is there a required list of COBie attributes?
No universal list. NBIMS-US V3 leaves the standardization of property sets outside COBie, and the COBie Guide says Attributes should match the product data on the contract deliverables. Use the design schedules, manufacturers' data sheets, and any properties the owner requires.
Can an owner require assets the US lists exclude?
Yes. NBIMS-US V3 notes that owners may extend COBie to non-managed facility assets and expects COBie to be customized to owner requirements. A contract-specific scope governs that project.
Sources and edition

This guide covers COBie 2.4 as published in NBIMS-US V3 by the National Institute of Building Sciences. It is an independent summary, not a reproduction of the standard. Where the standard, the contract, and the owner's requirements differ, follow the contract.

Sections cited: §4.2.1.2.3 Table 4, §4.2.3.2.2, §4.2.5.2.4.8 and 4.2.5.2.4.9, §4.2.6.2.1.34 and 4.2.6.2.1.35, §4.2.6.2.3, §4.2.7.15 with Tables 101 and 102, §4.2.8.1.3, and §4.2.9.1.1 and 4.2.9.1.2; Annex A Table 44, §A.4 with Tables 58 and 59, and §A.5.

National Institute of Building Sciences: NBIMS-US V3 COBie 2.4National Institute of Building Sciences: COBie 2.4 Annex A